The Project Breakdown Structure page allows the user to setup a Project Level Breakdown Structure. The user can view, import, or manually create a Project Breakdown Structure page by using the appropriate action links. By using the drop downs in the Project Breakdown Structure page, the user can view the Work Breakdown Structure, Organizational Breakdown Structure, and Risk Breakdown Structure for the current project.
Figure 1
Figure 2
There are mainly three breakdown structures; such as Organizational Breakdown Structure, Work Breakdown Structure and Risk Breakdown structure. These breakdown structures can be viewed, created, imported, edited and deleted. Each of these methods is explained in detail below:
This functionality is used to Import Breakdown Structures. This functionality is visible only if no node has been added to the breakdown structure.
Steps:
Sample sheet used for import:
WBS code |
Description |
Outline Level |
A |
ABC123 |
1 |
B |
ABC124 |
2 |
C |
ABC125 |
2 |
Figure 3
This functionality helps to create a breakdown structure manually using the tree structure. This functionality is visible only if no node has been added to the breakdown structure. To create a breakdown structure, click the Create link. (Figure 1) To add nodes, click the Add Node button (steps are described in detail in Add Node section). (Figure 2)
This functionality is used to add a new node.
Steps:
Figure 4
This functionality removes a node.
Steps:
This functionality is used to rename an existing node.
Steps:
Figure 5
This functionality is used to expand all the nodes under tree the structure.
Steps:
This functionality is used to collapse the expanded nodes shown in Figure 7.
Steps:
Figure 6
Figure 7
This functionality makes the level of the child node the same as that of the immediate parent. For example, consider the node 6: Foundation (Figure 8) which is a child of the node 5: Site Work. When promoted, 6: Foundation is on the same level as 5: Site Work (Figure 9). A node cannot be promoted if it does not have a parent.
Steps:
Figure 8
Figure 9
When a node is demoted it becomes the child of the node which is of same level and which lies just below it. For Example, consider the node 4: Grading & Building Permits (Figure 9), which is of the same level as the node 2: Document Review & Revision. When 4: Grading & Building Permits is demoted, it becomes a child node of the node 2: Document Review & Revision. (Figure 10) A node cannot be demoted if there is no other node of same level as the node selected.
Steps:
Figure 10
This operations used to move a node up. The Up Order can be applied only to nodes of the same level and this operation is not applicable for the first node. For example, consider the nodes 6: Foundation and 5: Site Work in Figure 10. The node 6: Foundation is located below the node 5: Site Work. When an Up Order operation is applied to the node 6: Foundation, it moves above the node 5: Site Work. Figure 11 shows the tree structure after the Up Order operation is applied.
Steps:
Figure 11
This operation is used to move a node down the tree structure. This can be applied only to nodes of the same level and this operation is not applicable for the last node. For example, consider nodes 1: Contracts and 2: Document Review & Revision in Figure 11. 1: Contracts is located above 2: Document Review & Revision in Figure 11. When a down order operation is applied to the node 1: Contracts, it comes below the node 2: Document Review & Revision. Refer to Figure 12, which shows the tree structure after a Down Order operation is applied.
Steps:
Figure 12
This functionality is used to delete the selected breakdown structure.
Steps:
This functionality is used to save the changes made to the Project Level Breakdown Structure.
This functionality is used to edit the tree structure. The User can perform operations such as add, remove, rename, expand, collapse, promote, demote nodes as well as change the orders of the nodes.
Steps:
Copyright © 2021 PRC Software. All rights reserved
This will close in 0 seconds
This will close in 0 seconds
The PRC Enterprise Risk Register is a web-based risk management software solution which allows for the tracking of risk at the project and portfolio level. Audit logs for all risk updates and changes are available at the click of a button to aid with audits, claims and the flow of information. The power of the PRC Enterprise Risk Register is in the simplicity of the user interface, which is designed to navigate easily at both project and portfolio levels without compromising functionality or data. The PRC Enterprise Risk Register allows for mapping across project levels so the data can be reported at the portfolio level, even if the work, risk and organizational breakdown structures are not standardized.
This will close in 0 seconds
The PRC Enterprise Cost Risk Analysis is a customizable web-based solution for simulating estimate cost and determining cost contingency, cost drivers, and risk hotspots. The key to a good risk analysis is good inputs. The software cannot be a roadblock to success. Good risk software should be easy on the end user. Monte Carlo simulation is already a complex. The software should simplify the process.
This will close in 0 seconds
The PRC Enterprise Schedule Risk Analysis is a customizable web-based solution for simulating schedule duration and dates. At PRC Software, we believe that the key to good risk software is through good inputs and excellent user friendliness. A Monte Carlo simulation is already a complex. The software should not be complicated as well.
This will close in 0 seconds
PRC specializes in risk analysis, audit, and training. We have cross-industry experience in fields such as Aerospace & Defense, Oil & Gas, and Engineering & Construction. We believe that over-complicating the risk process often leads to wasted effort and poor results. Our goal is to "make it simple."
This will close in 0 seconds